Discussion about this post

User's avatar
BRIAN CAM's avatar

VANDALS==Massachusetts WOKE Democract Rule ==The two 500-foot cooling towers at the former Brayton Point coal-fired power plant in Somerset, MA, cost approximately $600 million to build and were constructed between 2009 and 2011. They were imploded and demolished in 2019.

Construction: Construction began in 2009 and was completed in 2011.

Cost: The project cost approximately $600 million.

Purpose: The towers were built to reduce the amount of heated water discharged into Mount Hope Bay.

Demolition: The towers were imploded and demolished on April 27, 2019.

Plant Closure: The Brayton Point power plant ceased power generation and went offline on June 1, 2017. Massachusetts ERATE PAYERS still Paying.

Expand full comment
dave walker's avatar

Fight, fight, fight until we tip the scales in favor of common sense and reliable electricity!!! Green and renewable are big filthy lies!

Expand full comment
2 more comments...

No posts